Appendix 1
A Brief Outline of the History of the Bureaucracy of Water
Several city agencies have been referred to in this paper without explanation. In my own research, I found myself confused by the multiple agencies involved, as well as the time periods or areas in which these agencies worked. Moreover, I was intrigued by the manholes associated with both the Old and New Croton Aqueduct and associated water mains; some of these manholes are marked with DPW, others with WSNY, and still others with other cryptic acronyms. For the purposes of clarifying both this paper and the city infrastructure, therefore, I include this brief history of the agencies involved.
Originally the responsibility for hiring surveyors, engineers, and contractors for the first Croton Aqueduct was under "The Board of Water Commissioners." This board was created by the Common Council in 1834, and they commissioned the original surveying that showed the feasibility of using the Croton river, and later hired J. Jervis as the overseeing engineer on the project.
In 1842, as the aqueduct was being finished, the Common Council set up the "Croton Aqueduct Board," which was in charge of the distributing pipes, which carried the water throughout the city from the reservoir at 42nd Street and 5th Avenue.
On April 11, 1849 the Legislature created the "Croton Aqueduct Department." This Department was then responsible for the distributing pipes as well as the Aqueduct.
It must be recognized, of course, that responsibility for the water system does not mean independent power to actually do anything, and funding in particular requires going back to the other parts of the city bureaucracy. In 1846, for example, the Board of Water Commissioners first informed the city that another reservoir would be needed in Central Park (the original reservoir, on the site of the Great Lawn, was insufficient to supply the city for the several-day period needed to do a full inspection of the masonry conduit). However, it was not until 1851 that the Croton Aqueduct Department was authorized to use the land to build the new reservoir.
At the same time, the City was acquiring land for Central Park. The Water Commissioners had originally wanted a rectangular plot, from 86th to 95th streets and between 5th and 7th avenues; however, by special agreement with the Park Commission, the Aqueduct Department eventually used a plot that conformed to the shape of the land, which resulted in a 96-acre reservoir with a shape that is close to rectilinear. This is the present-day body of water in Central Park known as "The Reservoir." The ground for this reservoir was not actually broken until April 17, 1858, and it was put into service in 1862, 14 years after the Board of Water Commissioners had first articulated its necessity. This was actually quite speedy for a process that required cooperation between various departments of the citys government.
The Croton Aqueduct Department was superseded in 1870 by the Department of Public Works, which was created by Chapter 137 of the Laws of 1870. Most of the manholes associated with both the old and new croton aqueducts are marked with a "DPW," because a great deal of the water infrastructure was built or rebuilt at this time.
In 1883, the New Croton Aqueduct and Reservoir were put under the newly created Aqueduct Commission. However, this commission was created only to oversee these specific projects, taking place upstate, and so most of the visible water supply infrastructure within the city limits of New York was still under the auspices of the Department of Public Works.
In 1898 the city was consolidated with the outer Boroughs, and the Department of Water Supply, Gas, and Electricity (D.W.S.G.&E.) was formed. The Board of Estimate also authorized the issuance of $4 million in bonds to enhance the water systems in Brooklyn, drill wells in Queens and build a dam to create the Cross River reservoir.
It has been suggested, in fact, that a significant factor in Brooklyns willingness to join the consolidation was their lack of a suitable water source, in stark contrast to the free-flowing water in Manhattan. Despite the connections to NYCs water, some water-supply problems continued in Brooklyn and Queens, as well as in the rest of Long Island. There has always been some reliance on wells that draw water from the Long Island aquifer-- that is, the fresh water in the porous layers of the ground-- but over the years, the aquifer has been significantly reduced. Wire-making and other industries have disposed of chemical and industrial waste down "dry wells," and seepage from these holes has affected the water supply. More importantly, perhaps, so much of Long Island has been paved over that rainwater can no longer seep into the ground effectively to replenish the aquifer. Thus, the saline water from the ocean water table has seeped in to fill this vacuum, leaving a much shallower (and still shrinking) aquifer available to supply drinking water.
The Department of Water Supply, Gas, and Electricity did preliminary surveys on the expansion of the water systems, and then in 1902, Mayor Seth Low appointed an independent committee, the Commission on Additional Water Supply for the City of New York, to study the city's water situation. Their Report of November 30, 1903 was a massive document that, among other things, estimated that 40 mill gallons were lost each day and recommended universal metering and plumbing regulations and inspections. The report made it clear as well that whatever conservation was practiced, the expansion of the city would still necessitate further acquisition of water sources. It recommended therefore the examination of a number of potential sites for further expansion of the water supply.
Realizing that the city was going to try to grab more land and water, some upstate counties sought legislative protection from acquisition. At the same time, the state clarified and expanded the citys water-supply privileges. In 1904, for example, water bonds were exempted from the citys debt limit. In 1905, Chapters 723 and 724 of the Laws of 1905 were signed, including the McClellan Act.
These chapters also created the five-person State Water Supply Commission, authorized to approve or reject and New York City water plan.
Significant elements of the McClellan Act included the empowerment of the city to take possession of land and/or dwellings for the water system just ten days after giving notice, and required the city to pay owners only one-half of the assessed valuation of the property.
The McClellan Act also required the appointment by the Mayor of the Board of Water Supply to oversee the process of New York Citys water system development. This three-person Board hired engineers and planners and administrated the development of the Catskill system, even as the New Croton system was being completed. Although it was originally intended just to oversee the development of the Catskill system, this Board of Water Supply became a permanent agency in New York City.
However, the authority of the Board of Water supply is limited to the construction of new reservoirs, aqueducts, pumping plants, and other infrastructure. Thus when the Catskill system was completed, or when any other reservoir or pipeline was completed, it was turned over to the Department of Water Supply, Gas, and Electricity for maintenance.
Currently, control of New York Citys Water supply system is under the Department of Environmental Protection (DEP). Within the DEP, the Bureau of Water Supply (BWS) manages, operates, and protects the upstate portions of the water supply system. The Bureau of Water and Sewer Operations (BWSO), also within the DEP, maintains and operates all of the drinking water and wastewater systems in the City.
Appendix 2
Inverted Siphons
The idea of the inverted siphon is worth mentioning as it relates to the rest of the aqueduct. Most of the aqueduct was built essentially as a canal or trough with an arched brick roof, and was never intended to contain water under pressure. The high-water line was usually several feet from the roof of the aqueduct. This was one of the two reasons for ventilators along the length of the aqueduct, the other reason being to keep the water fresh on its two-day journey from upstate. But Jervis was worried as well that the moving water would push air ahead, and that this pressurized air would damage the roof of the tunnel. He made sure, therefore, to install either a ventilator or waste-weir every mile. He had few patterns to follow in this; it was still a new engineering problem. Worried that every mile might not be enough, he designed square holes in the brick aqueduct roof every quarter-mile, capping each one with a flat stone, so that if more ventilators were later needed, they could be added. This had an unforeseen effect later: when the needs for water increased before the New Aqueduct was online, the only solution was to pump more water through the Old Aqueduct, at one point up to 95 million gallons daily rather than the 60 millions gallons daily that had originally been intended as the maximum possible. In order to make this possible, the roof arches of the aqueduct had to be reinforced with another layer of brick and cement all along its route. Even so, leaks and cracks appeared.
At the inverted siphons, specifically High Bridge and Manhattan Valley, the force of gravity pressurized the water on the downhill, and forced it up to an equal height on the other side. However, this meant that at the low point, there was a great deal of force applied from the weight of the water on the pipe. Also, friction was much higher in these pipes; thus, in order to keep the water flowing fast enough, a drop of several feet was built into both of these locations. This drop in grade of several feet is significant when one considers that for the Bronx/Manhattan section, the intended slope of the conduit was only 13 inches per mile. Thus the inverted-siphon solution was used only when the significant savings in money made the loss of height worthwhile.
Appendix 3: Historical Signs from Parks
The Historical Signs shown below are quite recent innovations. They are of interest to the extent that they act as legible explanation of the park space, which can contain or signify (invisible) historical meaning.
The texts of all historical signs are available online at http://nycparks.completeinet.net/sub_your_park/historical_signs.html
MORTON PLAYGROUND
In the early 19th century, New York City grew faster and larger than any other city in the Western Hemisphere. Like most American cities of the time, New York suffered from an unreliable and polluted water supply. Terrible fires and recurring epidemics of yellow fever and cholera periodically devastated the city. In 1834 the state legislature approved a plan to use the Croton River as the city's water supply. Construction began in 1837 to build the Croton Dam, a 41-mile-long conduit, 114 stone culverts, numerous bridges and embankments, and reservoirs at Central Park and 42nd Street and Fifth Avenue (now Bryant Park). The Croton Aqueduct opened with great fanfare on July 4, 1842. The gravity-fed system, completed at a cost of about $13.5 million, was one of the greatest engineering feats of the 19th century.
The Croton Aqueduct stretched 41 miles from Croton Dam, through Westchester County and the Bronx, and into Manhattan. Most of the property which became the park known as "Aqueduct Lands" was acquired by condemnation between 1837 and 1838, with additional parcels annexed in 1895, 1953, and 1973. In 1930 the Department of Parks was given surface rights to the lands held by the Department of Water Supply, Gas and Electricity. Restrictions limited development to playground use and to light construction and planting.
The "shoestring" park--so called for its long and skinny shape--was developed in the 1930s and 1940s with paved paths, game tables, benches, handball courts, shuffleboard courts, and three playgrounds. The playground at Morton Place opened in 1947. Both street and playground were named for Thomas Morton, who bought part of the Benjamin Berrian farm in 1855. The Old Croton Aqueduct was closed permanently in 1965 and was listed on the New York State and National Registers of Historic Places in 1974. It was designated a National Historic Landmark in 1992, on the 150th anniversary of the New York Water Supply System.
In 1998 Council Member Adolfo Carrion Jr. funded the $650,000 reconstruction of Morton Playground. The playground design features sculpted beavers that serve as spray showers as well as a colored concrete map of the route of the Aqueduct, depicting landmarks along the former water route. The renovated basketball courts have new surfacing and hoops, and a new steel gate, adorned with a sculpture of Morton the Cat, protects the entrance.
April, 1999
Appendix 3
BARNHILL TRIANGLE
This triangle honors Reverend Oliver Paul Barnhill (d. 1934) who led the congregation at the Fordham Manor (Dutch) Reformed Church from 1924 to 1934. Reverend Barnhill was born in LaGrange, Kentucky and attended, in succession, Poplar Grove Academy, Center College, and Princeton University, where he received an M.A. He served as an assistant at the Memorial Presbyterian Church of Brooklyn for twelve years and as associate pastor of the Marble Collegiate Church from 1916 to 1923. Based on his credentials and what the New York Evening Telegram described as "an exceedingly agreeable personality," he was asked to serve as pastor of the Fordham Manor Reformed Church; he started on October 7, 1923.
Reverend Barnhill proved to be an able pastor. He was a moving and eloquent speaker, and had a knack for social organization. The church expanded with the purchase of the nearby Clarke house for use as a parsonage. The cost of this acquisition, however, drove the church into financial troubles. Reverend Barnhill led his congregation through the trauma of the Great Depression, but it proved to be his final task as a pastor. On Sunday, March 18, 1934, Reverend Barnhill gave what was reported to be a beautiful communion service, and subsequently died of a heart attack.
Barnhill Triangle sits on what was once a right-of-way for the Old Croton Aqueduct. The construction of the Old Croton Aqueduct was one of the greatest engineering feats of the 19th century. The Croton river was dammed and a forty-one mile tunnel and bridge structure was erected for the project; it opened in 1942. The aqueduct allowed for further growth and development of New York City by alleviating two of the city's worst problems: fire and cholera. The abundant supply ensured that enough water would be available to put out fires, and stop the epidemics caused by contaminated water. Although it was built to last for centuries, the Old Croton Aqueduct served the City for less than 50 years. It was doomed not by its engineering or construction, which were both superb, but by its own success: the aqueduct enabled New York to expand so rapidly and so successfully that it was unable to provide enough water for the exploding populace.
In 1890, the New Croton Aqueduct opened (essentially a tunnel blasted through rock), which eventually replaced the Old Croton Aqueduct. The old aqueduct continued to deliver water to Manhattan, gradually decreasing flow until 1955. While the aqueduct itself is no longer useful, its right-of-way was turned over to Parks and remains some of the city's oldest parkland. The transfer of right-of-way was made under the condition that the land be used only for "park and playground purposes." To that end, shrubs and trees, including Callery pears and London planetrees, have been planted in Barnhill Triangle and benches invite passersby to sit and enjoy the greenery.
Recently, Barnhill Triangle was renovated as part of the Greenstreets program. Initiated in 1986 and revived in 1994, Greenstreets is a program that plants trees and shrubs in some of the city's smallest parks, squares, and traffic islands and triangles.
November, 2000